Monday afternoon:
8 days in. most of the slates are replaced, and the sheeting is off the "hangar".

Tuesday morning:
The frame of the hangar is being cut down.

Tuesday afternoon:
The Hangar has gone and demolition of the first chimney starts.

Wednesday:
The chimney is demolished and work has begun on the hole over the stairs. This requires a bit of redesign so that the problems of rain entering the house don't reoccur. Work continues for 2 days

Friday morning:
The area over the stairs is finished.

Friday Afternoon:
The second chimney is demolished.

Simon